Week 43 progress report is for work completed up to the end of June. Works completed up to Week 43 included:
- 
Monitoring of safety, environmental, erosion and quality controls;
 - 
100% topsoil stripping completed;
 - 
100% earthworks cut and fill completed;
 - 
100% sewer trenching, pipe installation and construction of sewer manholes completed;
 - 
100% stormwater pipes layed and 100% stormwater pits installed;
 - 
100% sewer pump station components completed;
 - 
100% watermain works commenced and 100% of water services with connection still to occur;
 - 
100% subsurface drains completed;
 - 
100% demolition of entry house and clearing works completed;
 - 
90% of electrical works completed;
 - 
90% of road subbase construction completed;
 - 
90% of sewer rising main installation completed;
 - 
90% of NBN installation completed;
 - 
85% of kerb & gutter completed
 - 
10% of footpaths completed
 - 
Re-topsoiling of lots and verge commenced.
 



											
				