Yarrah Stage 1 Construction Update – Week 9
Works to week 9 have seen good progression with two solid weeks of good weather that enabled approximately 64 percent of general earthworks to be completed. The
Works to week 9 have seen good progression with two solid weeks of good weather that enabled approximately 64 percent of general earthworks to be completed. The
The past 7 weeks have been very busy onsite for Yarrah Stage 1 civil works with substantial rainfall experienced over September and October. Initial site works included
Stage 1 Civil Construction kicked-off at Yarrah, Yass in early September 2021. Civil works are being undertaken by Woden Contractors, who will delivery the entire stage including 62 residential lots,