Week 19 progress report covers the first two weeks of works after a two week site shut down due to the Christmas holiday break. As of week 19 works completed onsite include:
- 
Monitoring of safety, environmental, erosion and quality controls;
 - 
97% of topsoil stripping completed;
 - 
97% of earthworks cut and fill completed;
 - 
30% of sewer trenching, pipe installation and construction of sewer manholes completed;
 - 
10% Stormwater trenching underway;
 - 
Relocation of existing power lines through the site to enable continuation of earthworks.
 
											
				