Week 25 progress report is for works up until the end of February. A new up-to-date progress report is expected soon. Works completed up to Week 25 include:
-
Monitoring of safety, environmental, erosion and quality controls;
-
100% of topsoil stripping completed;
-
99% of earthworks cut and fill completed;
-
99% of sewer trenching, pipe installation and construction of sewer manholes completed;
-
100% stormwater pipes layed and 50% stormwater pits installed;
-
Watermain works commenced;
-
Subsurface drains commenced;
-
Sewer pump station components completed;
-
Demolition of entry house completed, minor clearing works remaining.