Week 54 progress report is for work completed up to the end of September. Works completed up to Week 54 included:

  • Monitoring of safety, environmental, erosion and quality controls;

  • 100% topsoil stripping completed;

  • 100% earthworks cut and fill completed;

  • 100% sewer trenching, pipe installation and construction of sewer manholes completed;

  • 100% stormwater pipes layed and 100% stormwater pits installed;

  • 100% sewer pump station components completed;

  • 100% watermain works commenced and 100% of water services with connection still to occur;

  • 100% subsurface drains completed;

  • 100% demolition of entry house and clearing works completed;

  • 100% of road subbase construction completed;

  • 100% of kerb & gutter completed;

  • 100% of NBN installation completed;

  • 95% of sewer rising main installation completed;

  • 99% of electrical works completed;

  • 95% of footpaths completed;

  • 85% topsoiling of lots and verges;

  • 5% of road top coats (prime/seal/AC);

  • 75% Retaining walls;

  • 50% Tree planting and landscaping.