Stage 2A is now complete and ready for building. The first houses are moving through design, planning and approval processes. House building is expected to start very soon.

See what’s available in Stage 2A: Visit Interactive Map

Stage 2A Title Registration occurred in November 2024.

Stage 2A Civil Construction commenced in March 2024 and is ongoing.

Stage 2A was awarded to Lentro Earthworks in January 2024.

Stage 2A Subdivision Certificate was approved in May 2023.

Stage 2A DA modification was approved in March 2023.

Stage 2A DA was approved in September 2022.